5501 FORWARD EXECUTION ROADMAP

5501 E. 33rd Development Execution Roadmap

A disciplined project index for site diligence, entitlement strategy, capital sequencing, consultant coordination, and construction readiness.

Geotech reviewedPhase II complete / targeted follow-upSealed ALTA received / title integration activeDURA agreement discussions advancingCapital narrative forming
Current Stage: Due Diligence + Market Validation
Site Studies: Geotech + Phase II Complete / Targeted Follow-Up
Public Sector: DURA Agreement Development
Entitlement: By-Right Control + Density Feasibility
Capital: $250K–$400K Predevelopment Discussion Range
Design Readiness: Scenario Test-Fit Preparation

Current Diligence Read

Phase II Complete

Commercial-use environmental uncertainty has materially narrowed. Residential vapor and former fuel-island / UST follow-up remain targeted planning items.

DURA Advanced

DURA Board authorized staff to proceed with final scope, potential funding, and Redevelopment and Disbursement Agreement discussions. Final funding remains subject to formal approval.

Next Capital Layer

Focus on entitlement, design, civil/utilities, market validation, cost confidence, site stabilization, and decision-ready capital materials rather than vertical construction.

Scenario Path

3 Story

By-Right Control Case

$8.3M–$10.4M

Lowest entitlement-height risk baseline.

6 Story

Primary Feasibility Case

$23M–$31.5M

Primary upside case under active feasibility review.

8 Story

Higher-Density Sensitivity

$41M–$57M

Sensitivity only unless added complexity is validated.

10 Story

Long-Range Sensitivity

$62M–$86M

Outer-boundary sensitivity; not a proposed base plan.

Execution Phases

Phase 1

Project Alignment

Project basis and early strategy confirmed.

Complete
Phase 2

Site Studies + Due Diligence

Geotechnical and Phase II complete; targeted environmental follow-up remains tied to the selected development program.

In Progress
Phase 3

Survey + ALTA / Title

Sealed ALTA received; title, access, utility, and consultant integration continues.

ALTA Complete / Title Review In Progress
Phase 4

Market + Product Validation

Validate product mix, pricing, affordability, retail, parking, and exit assumptions.

In Progress
Phase 5

Capital Readiness

Prepare disciplined predevelopment capital strategy and investor-ready decision materials.

In Progress
Phase 6

Entitlement + City Strategy

Compare the by-right control case against added-density pathways while DURA agreement discussions advance.

In Progress
Phase 7

Design Team Assembly

Coordinate architect, civil, engineering, GC, and specialty consultant scopes.

Queued
Phase 8

Concept Design + Massing

Test 3-, 6-, 8-, and 10-story planning scenarios against actual site constraints.

Queued
Phase 9

DD + Engineering

Advance the selected planning path into coordinated design development.

Queued
Phase 10

Permit + Financing

Align permit readiness with debt and equity requirements.

Queued
Phase 11

Preconstruction + Mobilization

Prepare field controls, procurement, schedule, and site logistics.

Queued
Phase 12

Vertical Construction

Execute the approved project through controlled construction milestones.

Queued
Phase 13

Closeout + Exit

Complete turnover and execute the final hold, sell, refinance, or other exit path.

Queued

Near-Term Priorities

  • Scope targeted environmental follow-up based on Phase II and selected development program
  • Integrate sealed ALTA with title, architecture, civil, utility, and entitlement review
  • Advance DURA scope and Redevelopment and Disbursement Agreement discussions
  • Validate 3-story control and 6-story primary feasibility cases through test fits
  • Develop conceptual construction pricing and market-supported economics
  • Prepare qualified investor / capital partner discussion materials