Phase II Complete
Commercial-use environmental uncertainty has materially narrowed. Residential vapor and former fuel-island / UST follow-up remain targeted planning items.
5501 FORWARD EXECUTION ROADMAP
A disciplined project index for site diligence, entitlement strategy, capital sequencing, consultant coordination, and construction readiness.
Commercial-use environmental uncertainty has materially narrowed. Residential vapor and former fuel-island / UST follow-up remain targeted planning items.
DURA Board authorized staff to proceed with final scope, potential funding, and Redevelopment and Disbursement Agreement discussions. Final funding remains subject to formal approval.
Focus on entitlement, design, civil/utilities, market validation, cost confidence, site stabilization, and decision-ready capital materials rather than vertical construction.
3 Story
$8.3M–$10.4M
Lowest entitlement-height risk baseline.
6 Story
$23M–$31.5M
Primary upside case under active feasibility review.
8 Story
$41M–$57M
Sensitivity only unless added complexity is validated.
10 Story
$62M–$86M
Outer-boundary sensitivity; not a proposed base plan.
Project basis and early strategy confirmed.
Geotechnical and Phase II complete; targeted environmental follow-up remains tied to the selected development program.
Sealed ALTA received; title, access, utility, and consultant integration continues.
Validate product mix, pricing, affordability, retail, parking, and exit assumptions.
Prepare disciplined predevelopment capital strategy and investor-ready decision materials.
Compare the by-right control case against added-density pathways while DURA agreement discussions advance.
Coordinate architect, civil, engineering, GC, and specialty consultant scopes.
Test 3-, 6-, 8-, and 10-story planning scenarios against actual site constraints.
Advance the selected planning path into coordinated design development.
Align permit readiness with debt and equity requirements.
Prepare field controls, procurement, schedule, and site logistics.
Execute the approved project through controlled construction milestones.
Complete turnover and execute the final hold, sell, refinance, or other exit path.